Update on Gemenskap Park

1124800_N2

We recently received an update from Seattle Parks that they are still on schedule to begin work on Gemenskap Park this Spring. Final corrections to the bid documents are in process. When complete, these documents will be sent to City Contracting. It then typically takes 2-4 weeks for review before they can advertise the bid. They are planning for a 4-week advertisement period with plans to hire a contractor and start construction in April. The time between bid opening and actual contracting will fluctuate based on contractor response time and the time it takes for them to prepare bonding and insurance requirements. We’ll continue to provide updates as we learn more.