A new schedule from the Seattle Parks Department for the 14th Ave NW Park is hot off the presses.
Here are some of the schedule highlights…
Early June 2014 – Submittal of drawings for 60% Street Improvement Process (SIP)
Mid September 2014 – Submittal of drawings for 90% SIP
Early December 2014 – Submittal of drawings for 100% SIP
Late December 2014 – Put out bid for contractors
Early April 2015 – Begin construction
Late September 30, 2015 – Construction complete!
If all goes as planned, we’ll be having a big celebration in our new Park by next Fall!